Case
Histories - Sliplining Saves Sewers in New Jersey
During
the summer months, tourists flock to the shore towns of Ocean County, N.J., to
enjoy the surf and sand. Its the job of the Ocean County Utilities Authority
(OCUA) to make sure there are no disruptions to this vital source of revenue.
OCUA
has a fleet of TV trucks as part of an ongoing program of sewer inspection. OCUA
spends about $3 million annually on sewer renewal, using cured-in-place piping,
sliplining and open-cut replacement, according to Knut Nielsen, project engineer
for OCUA. Recently, inspections revealed about 10,000 ft of 36-in. reinforced
concrete pipe along Route 9 in Bayville that was suffering from H2S
corrosion. The 25-year-old pipeline had deteriorated to the point where the steel
reinforcement was visible. Without
some sort of repair, a collapse was a possibility. OCUA implemented a $2 million
program to repair the line, of which about 2,400 ft was targeted for sliplining.
The area to be sliplined was adjacent to Route 9, a busy thoroughfare. Sliplining
was an attractive alternative because crews could construct the insertion pits
without disrupting traffic. Had the line been underneath the roadway, CIPP would
have been a more likely alternative, Nielsen said. In addition, one run
of pipe crossed underneath the roadway, so using CIPP would have required bypass
pumping across the road. Metra Industries/Spiniello was awarded the contract.
OCUA had previous experience sliplining with fiberglass pipe, but specified PVC
to evaluate its performance and cost-effectiveness. Lamson Vylon PVC Slipliner
with an ID of 30 in. was used by Metra/Spiniello. Weve
used PE slipliners in the past, but in this case the segmental liner turned out
to be more cost-effective because it eliminated the bypass pumping, said
Bob DePonte, Metra Industries/Spiniello project manager. To slipline
the damaged section, crews first had to build an insertion pit long enough to
accommodate the 15-ft segments. On this project, three insertion pits were constructed
for runs ranging from 300 to 800 ft. The limiting factor was the number of bends
because the flow provided buoyancy during insertion. If you have
good flow and good velocity, you actually have to hold the pipe back, Nielsen
said. Once exposed, crews removed the crown of the pipe so that the
slipliner can be lowered into the pipeline. Typically, a backhoe is used to excavate
the pit, lower the slipliner into position in the host pipe and then push it into
place. The Vylon slipliner is equipped with a locking feature so that each pipe
segment snaps together Bulkheads are also constructed at each end to constrain
the pipe. Once the pipe is sliplined, the annulus is filled with a lightweight
grout.
Most of the pits were constructed downstream of the manhole, but one segment presented
a unique problem. This section contained a 90-degree bend at the manhole, with
limited space between the manhole and the road. As a result, the crew constructed
the pit on the opposite side of the manhole and drilled through the wall of the
manhole to insert the slipliner Once the liner was in place, the crew repaired
the manhole wall. Metra Industries/Spiniello completed the sliplining
portion of the project, including restoration, in less than two weeks, Nielsen
said. |