Case
Histories - Boyer Perfects Tools for Houston Sliplining
Sliplining
is an unglamorous, low tech rehabilitation method. No sophisticated trucks with
shiny gadgets. No multi-stage launching devices. Not even a reprieve from the
flowing sewage. Despite its low-tech image and earthy applications, sliplining
continues to be a staple rehabilitation technique for effective, efficient renewal
of sewers and mains. And some contractors have found the way to make it into a
true niche of the construction industry. Boyer, Inc. of Houston, Texas
is one such contractor. In the last four years, Boyer has completed over 10,000
lineal feet of slip lined projects, mostly large diameter lines. Presently,
Boyer has undertaken two more projects totaling nearly 19,000 ft of sliplining,
nearly tripling his prior record of such work. And Boyer has found the methods
and developed the tools to give the company an edge in the sliplining market.
The Ben's Branch Sliplining Project in northern Harris County, near
the Houston Intercontinental Airport, involves 13,423 ft of line renewal, most
of it by sliplining, for the sanitary sewer serving the Kingwood Estates development.
The main is 24 to 48-in. in diameter and has a flow rate of three to four million
gallons per day. The project owner is the Harris County Utility District No.5.
A second project which Boyer is involved with is a portion of the City
of Houston Project No.4420-1 (Old Spanish Trail) sewer slipliner project. Boyer
has a contract for lining 5688 ft of a 60in. monolithic combined storm sewer.
The Ben's Branch project involves original clay and reinforced concrete
pipe. The new line is 18 to 42-in. elastomeric, gasketed, jointed Lallson Vylon
PVC profile-wall pipe with flush slip line couplings. A competitive
bid requirement for the $2.5 million project was that contractors were required
to bid with two sliplining alternatives. The consulting engineer, Ronnie Patrick
of Civil Concepts, Inc., South Houston, recommended and the owner selected the
Lallson Vylon product. In addition, all 57 manholes on the nearly three miles
of main are to be replaced in Boyer's contract. Mark Boyer, president
of Boyer, Inc., pointed out that this project is unique in a number of respects.
The project right of way borders on the rear of the established Kingwood subdivision,
following fences and electric power lines on the fringe of a dense overgrowth
of trees next to a drainage creek. This has required the transport of all materials
and pre-cast manholes on undeveloped drives along the ROW with an all-terrain
vehicle Boyer adapted from an old surplus military tank retriever. The
existing line also includes some sections in which a soft-lining rehabilitation
product had been installed within the past three years but had failed to provide
structural support for the deteriorated pipe. Boyer will remove these sections
before the new line can be slipped into place. Hydrogen sulfide corrosion
has taken its toll on much of the original RCP line. According to Boyer, in certain
conditions, hydrogen sulfide and sulfuric acid will deteriorate RCP in 20 years
or less. When corrosion reaches the reinforcing steel, the pipe deteriorates rapidly.
Joints fail, gaskets fall in and infiltration is soon rampant. On this line, 25
percent of the flow is judged to be from infiltration sources, said Boyer.
Boyer, Inc. has three crews working on the Ben's Branch project. One crew
excavates, removes old manhole structures, and prepares pits for sliplining. A
second crew rebuilds new manholes. The third crew carries out the sliplining process,
which includes cleaning the line, inspection, and installation of the pipe. Emmitt
Malmay is the project superintendent. Malmay described the process for
a typical sliplining project. It usually requires one day to dig the insertion
pit and set the 24-ft trench box and sheeting. Once the sewer line is exposed,
the top half of the original pipe is cut away to permit inserting sections of
new slipliner pipe. The second phase requires thorough cleaning, removal of obstructions
or point repair, and inspection. Sliplining is the next step, usually taking only
a few hours. Grouting the annular space is the final phase, and is done by a subcontractor.
Line inspection on this project was done by Coastal Contractors, Inc.,
Dickinson, Texas. Coastal used a trackmounted Peerless TV inspection unit to do
the video inspection. Once obstructions are identified in the line,
Boyer crews make a decision whether to spot-repair it or to remove the obstruction.
Malmay pointed out that pit location can be planned where a particular obstruction
exists which then can be manually removed. For example, a slipped joint was removed
in an insertion pit at a substantial savings over the cost of spot-repair.
One of the procedures developed by Boyer, Inc. is a new cleaning method.
Mark Boyer explained that, in his opinion, there are no readily available, effective
systems for cleaning large diameter lines. He has developed a specialized 2 cubic
yard bucket formed to fit the invert of the line which is pulled through to clean
the line. The new process permits cleaning a 500-ft line section in days, while
the old conventional bucket line approach may take weeks to clean the same line.
Malmay confirmed the efficiency of the new bucket method. A 340-ft reach
of 30-in. pipe, which was approximately half-filled with sand, was cleaned in
only two days. Before the pipe is sliplined, Boyer pulls a mandrel through
the reach to ensure that the new pipe will move freely into position. This mandrel
is simply a standard 15-ft joint of Vylon pipe which has been reinforced with
metal straps and a pull chain. Another Boyer developed sliplining tool
is a specialized hydraulic winch system to provide pulling force for the line.
A downhole roller assembly on the winch keeps the cable centered for true pulling
to avoid binding or abrading the new pipe being slipped. Boyer has patents pending
for the several specialized tools he has developed. Since all manholes
were to be replaced, this was a major part of the Ben's Branch project. Groundwater
at 8 ft below surface called for dewatering each site before excavation could
begin. The subcontractor Hunter Wellpoint of Crosby, Texas provided dewatering
services for the digging of pits. The pre-cast man holes which were
specified with a T-lock PVC lining, were supplied by Moor- Tex Concrete, Sealy,
Texas. Pipe entry points into the manholes were furnished with A-lock rubber gaskets
to provide watertight seals. As the manhole installations are completed,
grouting vent pipes are installed into the existing line. The vents permit the
evacuation of water from the annular space as the low-density, cellular foam grout
is pumped into the lines. Grouting services were provided by Gulf Coast Grouting,
a licensee of Pacific International Grouting. Sliplining runs on this
project varied from about 150 to 340 ft. A crucial step in the process, according
to Malmay, is making up the joint from one pipe section to another. A poorly joined
pipe may cause a line deflection or allow inflow of grout through a partial joint.
After the lead section is in place, Boyer uses small air bags inserted
into the carrier pipe to hold the liner in place. The new pipe section is pulled
into place, requiring about 1000 lbs. of pressure to make up the joint. When complete,
the air bags are released and the new sliplined pipe string is positioned.
An advantage of slip lining over other sewer relining methods is that the
flow does not need to be stopped or bypassed in order to carry out the process
explained that they may need to temporarily restrict the flow in order to complete
their work. However, at no time is the flow stopped. By late July, Boyer
was at the halfway point of the overall project schedule. Twenty-one of 57 manholes
had been replaced. Project superintendent Malmay reported that the slip lining
was ready to move to the 30-in. Vylon pipe. A 1574 1f portion of the overall project
specified as open-cut also had been completed. One of the claims favoring
sliplining is the purported improved flow efficiency of the new pipe over the
probable poor performance of the old host pipe. While the smaller diameter of
the slip lined pipe reduces the cross-sectional area, the improved flow characteristics
may compensate for the loss of capacity, and even improve the ultimate capacity.
Boyer, Inc. started in 1985 as an electrical construction firm. Mark
and his mother Lyda founded and are partners in the business. A CPA, Lyda is the
financial manager while Mark is the salesman and business development person of
the firm. Boyer employs approximately 100 people and maintains five crews.
The company performs civil, electrical, and mechanical work, including all
types of underground construction. Electrical construction now represents only
30 percent of Boyer's contract load. Their projects include electrical, gas and
water distribution work, wastewater treatment plant construction, and even boring
and jacking of large diameter storm sewer tunnels. Mark Boyer reports
that sliplining has made considerable headway throughout the Gulf Coast region.
With the specialty tools Boyer has developed and the benefit of substantial project
success, his company is positioned to lead in this pipe rehabilitation method
long after the Ben's Branch project is completed.
|