Case
Histories - Vylon Provides Better Option
Bellevue,
Nebraska, gateway to the upper Missouri and the fur trade empire, IS the oldest
continuous settlement in Nebraska, is a burgeoning residential community that
is home to the Offutt Air Force Base and STRAT-COM Headquarters, the center of
defense for the western world. As
a growing city, Bellevue is an established residential community with all the
same environmental concerns and demands on its infrastructure as any other community
in the United States. The July 1993 flooding of the Missouri River strained the
infrastructure and almost washed away the city's Haworth Park. The wastewater
systems are maintained by the Bellevue Public Works under the guidance and direction
of Dennis Hilfiker. The city was recently faced with the costly burden
of a deteriorating sewer system that had been experiencing high amounts of infiltration
for many years. Constructed during the 1950's, the existing system was comprised
primarily of concrete pipe. Hilfiker
contracted Omaha, Nebraska based consultants, Kirkham-Michael & Associates to
develop the project plans and specifications to replace the deteriorating sanitary
sewer trunk with anew and larger interceptor for one of the city's drainage areas.
Plans and specifications were developed for the Mud Creek Sewer Interceptor,
a project consisting of 13000 linear feet of 21-through 36-inch gravity sewer
pipe. A leakage allowance was specified to curtail ground water infiltration and
expensive treatment costs. The project was competitively bid and the successful
bidder was Andrus Enterprises Inc. of Omaha" Nebraska. Andrus was awarded the
project based on using reinforced concrete pipe (RCP) with the "0" ring gasket
and a "R-4" sewer joint. This is the standard RCP joint in the region which meets
the 200 gallon/day per inch-diameter leakage allowance. Soon after Andrus Enterprises,
Inc. began installing 36-inch concrete pipe along Mud Creek, they experienced
problems keeping the pipe on grade because of unstable soils and a high water
table. There were many leaking joints that had to be repaired by the concrete
pipe manufacturer to pass the exfiltration test. Meanwhile, 21-inch
Vylon pipe was being successfully installed on a similar project in the City of
Bellevue. Upon hearing of the problems facing the Mud Creek project team, Lamson
Vylon Pipes marketing and technical staff contacted Andrus Enterprises, Inc. and
supplied them with bedding requirements for the unstable area and competitive
pricing for the pipe. Lamson Vylon Pipe recommended an undercut of approximately
15 - to 18-inches. The undercut was filled with 1 1/2 -inch minus crushed stone
(well grated) on top of a geogrid and up to 6-inch below the pipe. Next, 3/4-inch
minus crushed stone was then used from 6-inches below the pipe to 6-inches over
the top in a trench that was one foot wider than the pipe's outside diameter.
The bedding recommendation stabilized the Mud Creek foundation and Andrus Enterprises,
Inc. successfully installed 24-inch Vylon pipe where 24-inch RCP, had sunken off
grade. Lightweight, closed profile Vylon pipe was installed at a much faster production
rate than then concrete pipe. Vylon pipe passed the initial 5% deflection test
and, one year later, was re-mandrelled successfully. "Large
diameter, PVC, closed profile pipe has made an immediate impact on Bellevue and
the surrounding area...with zero leakage jointing system, superior chemical resistance,
and the ability to be in stalled in deep, wet conditions, we will specify Vylon
pipe on future Bellevue projects," said Hilfiker. Vylon pipe was further
used to replace concrete pipe located in landscaped residential lots of this developing
community. The concrete pipe was continuously falling the exfiltration test and
dramatically slowing the project down. Facing liquidated damages, Andrus Enterprises,
Inc. removed the concrete pipe and within 24 hours had successfully installed
and air-tested 454 linear feet of 24-inch Vylon pipe. Vylon pipe is available
in long lengths that reduce the number of joints needed and allow for faster,
more efficient installation. Vylon pipe also provides a smoother internal wall
surface that minimizes fluid friction and flow resistance. This hydraulic smoothness
inhibits slime buildup and thereby lowers sewer maintenance costs. According to
Curt Andrus of Andrus Enterprises, Inc., "The bedding recommendations from Lamson
Vylon Pipe stabilized the foundations. The lightweight, closed profile PVC pipe
was installed at a much higher production rate than concrete. Vylon pipe air tested
perfectly...that's why we switched from concrete to Vylon pipe." Ease of installation
and superior performance of Vylon pipe eliminated any fears of late charges. The
contractor finished the project with 3,300 linear feet of 21-inch through 24-inch
Vylon pipe. Eight-inch through 24-inch pipe supplied by Lamson Vylon
Pipe was also used on the city's Squaw Creek Interceptor and the 25th Street and
Child's Interceptor. The new interceptors eliminated seven lift stations that
will reduce the city's maintenance budget and reduce capital outlays.
The decision to use Vylon pipe can be attributed to performance characteristics
of the product combined with the technical expertise provided by Lamson Vylon
Pipe. PVC Vylon pipe is engineered with deep insertion, gasketed joints that provide
superior resistance to costly leakage. Infiltration is a problem in Bellevue.
One joint leaking one gallon per minute equals over 500,000 gallons per year.
With the cost of sewage treatment today, that's a very expensive leak. One leaking
joint can easily add several thousand dollars a year to the cost of operating
the treatment plant. Leaking joints overload the treatment plants, steal the capacity
of the collection lines and cause the streets to cave-in when the soil washes
into the pipe. Vylon pipe bends or flexes when subjected to external loads rather
than cracking, breaking or shearing. Not only does the ability to flex serve to
eliminate fracturing and leakage associated with cracking, but Vylon pipe's flexibility,
in combination with the surrounding soil, enables it to sustain loadings that
would crush rigid pipes. Typical pipe embedment conditions will permit loadings
approaching 6,000 lbs. per square foot (50 ft. depth), without excessive deformation.
In addition, PVC Vylon pipe provides exceptional durability. Vylon pipe is
resistant to virtually all chemical attacks found in both domestic and industrial
wastewaters. Sulfide~e corrosion does not occur with Vylon pipe and abrasion wear
has been observed as insignificant. Years of research and development, hands-on
experience, and dependable products have made Vylon pipe the preferred sliplining
system. Lamson Vylon Pipe Technical Services IS staffed to analyze any particular
project needs. They provide finite element analysis, suggested bedding material
analysis, services, post installation inspections, and much more. Lamson
Vylon Pipe has been making quality pipes for more than 30 years, and was the first
manufacturer of 18-inch PVC gasketed sewer pipe. Large diameter Vylon pipe is
an extension of the company's proven technology. Produced in 13 feet length sections,
Vylon pipe derives its strength from a superior profile wall construction that
enables Lamson Vylon Pipe to produce Vylon pipe in 21-inch through 48-inch diameters.
All sizes meet and exceed ASTM D -3212 joint tightness requirements. The long-term
ability of Vylon pipe to meet "zero-leakage" criteria, resist corrosion, provide
excellent flow rates and reduce operating and maintenance costs, has enabled Lamson
Vylon Pipe to provide better options for cities across North America. |