Case
Histories - Sliplining Helps Restore Aging Sewer Lines
After
surveying the condition of the East Baton Rouge Parish sewer system, the Baton
Rouge Department of Public Works concluded that many of the interceptor sewers
placed into service over the last 70 years needed repair or replacement.
Video inspection and flow monitoring of the reinforced concrete pipe (RCP) and
vitrified clay pipe (VCP) used in the system showed that sections were leaking
badly because of cracked and broken joints, severe corrosion and misalignment.
Shread-Kuyrkendall & Associates Inc. of Baton Rouge was retained by the city
to prioritize the lines for repair. Based on the firm's report, 28 sewer lines
were selected for rehabilitation. Shread-Kuyrkendall recommended that either sliplining
or cured-in-lace linings be used to repair the lines. Hartec Corp., a
local Baton Rouge contractor, landed the project. The company chose to reline
the pipes with Vylon Slipliner segmented PVC pipe, in part because the pipe could
be installed without bypass pumping. Hartec called in Line One Inc.,
of Lewisville, a sliplining specialist, to assist with the project. Line One performed
the pre-inspection, cleaning and sliplining. Hartec constructed the insertion
pits, controlled traffic and grouted the annular space between the slipliner and
the existing conduit to hold the new pipe in place. Together the companies sliplined
7,900 linear feet of failing sewer pipe 24 in. to 54 in. in diameter. The repaired
sections ranged from 200 to 600 feet in length and included one section under
Route 110 north of Interstate 10. Condition
of Existing Pipe According
to Greg Strudwick, owner of Line One, "It was only a matter of time before all
28 sections of pipe would no longer be able to hold up the ground above them."
Strudwick noted that trunk lines are more vulnerable than other pipelines.
"In sewers with diameters larger than 15 inches that have turbulent flow, gases
are released promoting acid production at the crown that eats away the concrete.
As the concrete is devoured, the pipe's wire reinforcement begins corroding and
the structural integrity of the pipe is threatened," he said. "Moreover, the surface
roughness, due to pitting, slows the rate of flow. When our crews got in there
to clean, between the debris and the condition of the walls of the pipe, the line
was carrying onehalf to two thirds its capacity." Although sliplining
reduces the inside diameter of the pipe, the reduced inflow and infiltration combined
with the smooth interior surface of the slipliner actually increases the line'
s capacity for wastewater. "I was amazed at the improved flow after we
completed each line," said Chris Hicks, Executive Vice President of Hartec. "In
many lines, flow was enhanced by 35-40 percent." Installation
Excavators
were used to dig insertion pits and lower pipe sections. Pits were 1012 feet wide,
25 feet long and 15-20 feet deep. Hartec used stacked trench boxes, sliding 1-inch
thick plates on the open ends and behind the box walls. "With saturated soil,
we wanted to make sure it wouldn't flow in under the box walls or around the existing
pipe," Hicks said. "It would endanger the workers standing in the pit and also
eventually migrate into the recently cleaned line." Because work took
place during Baton Rouge's dry season, no dewatering was necessary. With trench
protection in place, workers entered the pit and removed the top of the old pipe
using sledgehammers and jackhammers. Cleaning buckets were pulled through the
line with a pneumatic winch. After removing the debris from the line,
the Vylon slipliner was lowered, joints assembled and the pipe pulled into place.
The majority of the slipliner was pulled with a winch downstream from an upstream
insertion pit. "Pulling the pipe in the direction of the flow seemed
to be the most fluid way to move and position the pipe," Strudwick said. "However,
some short pushes upstream were necessary , usually at the end of a segment or
when making closure." During insertion, the previously installed joints
were left protruding about 2 feet into the pit and inflatable lifting bags were
positioned at the spring line between the host pipe and the slipliner pipe. When
inflated, the bags anchored the slipliner train in place during assembly.
Workers lubricated the gasket and bell of the slipliner with subaqueous lubricant,
lowered and positioned the next section of slipliner and winched the joints together.
Closure pieces were constructed in the field when 15 feet or less were required
to complete a section. After the slipliner was installed, a lightweight,
cellular grout was pumped between the host pipe and the slipliner. Bulkheads were
built at the end of each line segment to contain the grout and prevent sewage
from entering the annulus. Three 2-inch tubes were built into each bulkhead. The
grout was fed through the center tube at the 12;00 position. The other two tubes
served as vents at the 10:00 and 2:00 positions. |